Liontown SRG Global
Shutdown Dashboard
Kathleen Valley Lithium Operation · Maintenance Support Services
LTR00XXX-SCH2-SOW · V5
Wet Plant Major Shutdown KV Processing Plant · 84-hour window · day & night shift · SRG Global Asset Maintenance
Shutdown window 17–20 Jun 2026

Programme Progress

Weather & Lifting Outlook

Live from Open-Meteo · gusts cross-referenced with crane lift limits

Scope of Work

Per Liontown Shutdown SOW (LTR00XXX-SCH2-SOW)

SRG Global provides suitably skilled and experienced personnel, tooling and equipment to undertake planned shutdown maintenance at the KV Process Plant, working cohesively with the Liontown permanent maintenance team. This dashboard tracks the live Wet Plant Major Shutdown — an 84-hour continuous event across day and night shift.

  • Mechanical Fitters · Boilermaker/Welders · Electricians & Instrument Techs · Trades Assistants
  • Supervision, scaffold & rigging access, itinerant plant (crane, EWP)
  • Shutdown tool container & tool store person
  • 12-hour shifts · 05:30–17:30 day / 17:30–05:30 night

Milestone Register

Key shutdown milestones & status

Shutdown Programme

Interactive Gantt — mobilisation → execution → demobilisation

Daily Shift Reports

Continuous dated feed — newest first · milestone days highlighted

Contract Notices

Register of shutdown notifications, variations, RFIs & back-charges

Controlled Document Library

Reference documents per Liontown Shutdown SOW. Drop files into the matching assets/ folder and link them here.

Health, Safety & Training

  • Health, Safety & Training Management Plan (HSTMP)SRG-HST-MP
  • Site Access ProcedurePRC-HS-C.000-0010
  • Alcohol & Other Drug Management ProcedurePRC-HS-C.000-0012
  • Infectious Diseases Management PlanSRG-IDMP
  • Contractor Management PlanPLN-HS-C.000-0003

Methodology & Work Method

  • Shutdown Execution Plan — Wet Plant MajorSRG-SD-EXE
  • Isolation & Lockout MethodologySRG-ISO-001
  • Lift Studies & Rigging PlansSRG-LIFT
  • Journey Management PlanFRM-HS-C.000-0006

Quality / QA-QC

  • Inspection & Test Plans (ITPs)SRG-ITP
  • Welding & NDT RecordsSRG-NDT
  • Post-Shutdown Report (template)SRG-PSR

Environmental & Social

  • Environmental Management PlanPLN-ES-C.000-0002
  • Hazardous Chemicals ProcedurePRC-HS-C.000-0017
  • Cultural Induction (Tjiwarl)KV-CULT

Key Contacts

Site leads & offsite escalation

By-Trade Workforce Summary

Planned vs confirmed vs contingency, with readiness status

Confirmed vs Open vs Contingency

By trade group

Shift Split & Ticket Coverage

Day/night split of mobilised crew · % holding each ticket

Personnel

Filter by group, shift or ticket held

Risk Register

Auto-generated from workforce, experience & records data

Experience Ranking by Trade Group

Tiers — Lead (8+ SD) · Senior (5–7) · Competent (2–4) · Developing (0–1)

18-Day Shutdown Roster

08–25 Jun 2026 · mobilisation → execution → demobilisation · open positions shown as amber TBC rows

Competency & Training Matrix

Per SOW Clause 9 — tickets & competencies held by mobilised personnel. ✓ = held · click a VOC cell to view verifications. Add file paths in js/gantt.js to make ticks click-to-view.